Before a landlord of residential flats in England carries out major works that will cost any one leaseholder more than £250, it must consult the leaseholders under section 20 of the Landlord and Tenant Act 1985 and the Service Charges (Consultation Requirements) (England) Regulations 2003. The same applies to long-term agreements, such as a cleaning or lift maintenance contract lasting more than 12 months, that will cost any leaseholder more than £100 in a year. If the landlord does not consult properly and the tribunal does not excuse it, each leaseholder’s contribution is capped at £250 for the works (or £100 a year for the agreement), however much the works actually cost.
This guide explains when section 20 applies, the three consultation stages and their time limits, what rights leaseholders have at each stage, what happens when landlords get it wrong and how dispensation works. If major works are already the subject of a disagreement, our property disputes team acts for leaseholders and landlords on consultation and service charge claims.

A section 20 notice is not the old Housing Act notice
Searches for “section 20 notice” mix up two different things. Under the Housing Act 1988, landlords once had to serve a “section 20 notice” on a tenant before an assured shorthold tenancy began. That requirement was abolished for tenancies granted from 28 February 1997 and has nothing to do with major works. When a leaseholder in a block of flats receives a section 20 notice today, it is almost always the first stage of consultation under the Landlord and Tenant Act 1985, telling them the landlord intends to carry out works or enter into a long-term contract.
When does section 20 consultation apply?
Consultation is needed in two situations:
- Qualifying works. Works on a building or other premises (repairs, maintenance, improvements, redecoration and the like) where the cost will result in any leaseholder’s contribution being more than £250.
- Qualifying long-term agreements. Contracts entered into by or on behalf of the landlord for more than 12 months, such as managing agent, cleaning, lift maintenance, energy or insurance arrangements, where any leaseholder’s contribution will be more than £100 in an accounting period.
The threshold is per leaseholder, not per building. In a large block, works costing tens of thousands of pounds might still fall below £250 per flat. In a small conversion, a single roof repair can easily trigger it. The rules apply to landlords of dwellings with variable service charges, and they bind resident management companies and right to manage companies as well as freeholders. They do not apply to commercial leases, where the tenant’s protection depends on the lease itself; our commercial property litigation team deals with service charge disputes on that side.
Landlords cannot avoid the threshold by splitting one project into smaller jobs. Whether a series of works is a single set of qualifying works is a question of fact, and the tribunal will look at what was really planned.
The three stages of consultation for major works
The procedure most leaseholders meet is the one for qualifying works that are not carried out under an existing long-term agreement and do not require public procurement notice. It is set out in Part 2 of Schedule 4 to the 2003 Regulations. Each notice must go to every leaseholder and to any recognised tenants’ association.
| Stage | What the landlord must do | Leaseholders’ rights | Time limit |
|---|---|---|---|
| 1. Notice of intention | Describe the proposed works (or say where they can be inspected), explain why they are necessary, invite observations and invite leaseholders to nominate a contractor. | Make written observations; nominate a contractor from whom the landlord must try to obtain an estimate. The landlord must have regard to observations received in time. | 30 days from the date of the notice |
| 2. Statement of estimates | Obtain estimates, including from a nominated contractor where required, and provide a statement setting out at least two of them. At least one must come from a person wholly unconnected with the landlord. Summarise the observations received and the landlord’s response, and make all the estimates available for inspection. | Inspect the estimates and make written observations on them. The landlord must have regard to them. | 30 days from the date of the notice |
| 3. Notice of reasons | If the contract goes to anyone other than a nominated contractor or the lowest bidder, explain why and summarise any observations on the estimates with the landlord’s response. | Information only, but the reasons can be relevant evidence in a later reasonableness challenge. | Within 21 days of entering into the contract |
The whole process for a straightforward project therefore takes at least two months before a contract can be signed, and usually longer once tendering is factored in. Other versions of the procedure apply where works are carried out under an existing long-term agreement (a shorter process with a single notice), where the landlord is entering into a long-term agreement itself, and where public procurement rules require a public notice, which mainly affects local authority and housing association landlords.
How to respond to a section 20 notice
The consultation period is the leaseholders’ best opportunity to influence the works and their cost. Once a contract is signed, it is much harder to change the scope or price. When a notice arrives:
- Diarise the 30-day deadline. It runs from the date of the notice, not the date you received it.
- Check the lease. Is the landlord actually obliged, or entitled, to carry out these works and recover the cost through the service charge? Improvements, for example, are often not recoverable unless the lease says so.
- Ask questions in writing. Why are the works needed now? Is there a survey or specification? Would a repair do instead of a replacement? Are any costs covered by insurance, a warranty or a building safety fund?
- Consider nominating a contractor. Leaseholders, individually or through a tenants’ association, can nominate a contractor. This is one of the few direct ways to introduce competition on price.
- Coordinate with your neighbours. A joint response carries more weight and shares the cost of any professional input, such as a building surveyor reviewing the specification.
- Keep copies of everything. If the cost is later disputed, the consultation record is key evidence for both sides.
What happens if the landlord does not consult properly?
If the consultation requirements have not been complied with, or dispensed with by the tribunal, the amount each leaseholder can be charged for the works is limited to £250 (or £100 per accounting period for a long-term agreement). For a project costing many thousands of pounds per flat, that is a significant protection, and it is the reason landlords who have missed a step usually apply for dispensation rather than absorb the loss.
Common failures include notices that do not describe the works adequately, consultation periods shorter than 30 days, estimates that were all from connected contractors, ignoring a leaseholder’s nomination, and starting the works before consultation finished.
Dispensation under section 20ZA
The landlord can ask the First-tier Tribunal (Property Chamber) to dispense with all or any of the consultation requirements if it is satisfied it is reasonable to do so. Applications can be made before works start, for example in an emergency such as a dangerous roof or failed boiler, or after the event where a step was missed.
The leading case is the Supreme Court’s decision in Daejan Investments Ltd v Benson [2013] UKSC 14. The court held that the tribunal should focus on whether the leaseholders suffered real prejudice because of the failure to consult, rather than on the seriousness of the landlord’s breach. Leaseholders have to identify what they would have done differently had they been properly consulted and how that would have made a difference; once they raise a credible case of prejudice, it is for the landlord to rebut it. The tribunal can also grant dispensation on conditions, such as reducing the recoverable cost or requiring the landlord to pay the leaseholders’ reasonable costs of investigating and opposing the application.
In practice, that means dispensation is granted in many cases. Leaseholders who want to resist it need specific evidence, not a general objection to the landlord’s conduct.
Consultation does not make the cost reasonable
A properly run consultation does not stop leaseholders challenging the works later. Service charges must still be reasonably incurred, and the works must be of a reasonable standard, under section 19 of the 1985 Act. Leaseholders can apply to the tribunal for a determination of what is payable, before or after the works are done. Our guide to challenging your service charges explains the grounds, and our guide to the First-tier Tribunal (Property Chamber) covers how applications work, the fees and the costs rules.
The two arguments often run together: a leaseholder might say both that consultation was defective and that the cost of the works was unreasonable in any event.
Building safety works
For many residential buildings at least 11 metres or five storeys high, the Building Safety Act 2022 restricts what can be passed on to leaseholders with a “qualifying lease” for historical building safety defects, and some leaseholders are fully protected from the cost of remediating unsafe cladding. Where a section 20 notice relates to fire safety or cladding works, check whether these protections apply before assuming the cost is recoverable through the service charge. The rules are detailed and depend on the building, the lease and the leaseholder’s circumstances on 14 February 2022.
Buying a flat with major works on the horizon
For buyers, a recent or pending section 20 notice is one of the most important things to find before exchange. A large bill for works that are already planned will usually fall on whoever owns the flat when the demand is issued, unless the contract or a retention deals with it. Your conveyancer should ask the seller and the managing agent about planned works, reserve funds and any current consultation. We set out what to look for in buying a leasehold flat: what your solicitor should check.
Reform: what is changing
The Leasehold and Freehold Reform Act 2024 includes amendments to the service charge provisions of the 1985 Act, including section 20, that are not yet in force. Separately, regulations laid in November 2026 introduce new rights for leaseholders to request service charge information from 1 April 2027, and standardised service charge demands, annual reports and accounts from private landlords from 1 November 2027. Those changes should make it easier for leaseholders to see what is being spent and planned, including on major works. The government’s Commonhold and Leasehold Reform Bill, introduced to Parliament on 19 November 2026, contains further proposals; as a Bill, none of it is law yet.
Frequently asked questions
Can the landlord start work before consultation finishes?
Only at its own risk. Unless the tribunal grants dispensation, the landlord’s recovery will be capped at £250 per leaseholder. In a genuine emergency, the usual course is to carry out the urgent work and apply for dispensation promptly.
Do I have to pay the full cost up front?
That depends on the lease. Many leases allow the landlord to demand estimated costs in advance or to draw on a reserve fund. A demand is only payable if it complies with the lease and the statutory requirements, including being accompanied by the summary of tenants’ rights and obligations.
Does section 20 apply to right to manage and resident management companies?
Yes. A company that takes on the landlord’s management functions takes on the duty to consult, so leaseholder-run buildings must follow the same process.
What if only some leaseholders were sent the notices?
Notices must go to every leaseholder who will contribute. A leaseholder who was not served can rely on the failure, subject to any dispensation the tribunal grants.
What are the three stages of a section 20 notice?
For most major works the stages are a notice of intention, a statement of estimates and, where needed, a notice of reasons. The first two each give leaseholders 30 days to make written observations, and the first also invites them to nominate a contractor. The notice of reasons is only required if the landlord does not choose the lowest estimate or a nominated contractor, and must be given within 21 days of entering into the contract.
Next steps
Section 20 consultation exists to give leaseholders a real say before large sums are committed. The time to act is when the first notice arrives, while the scope and contractor are still open. Landlords and managing agents, for their part, avoid expensive dispensation applications by getting each stage right first time. We advise both sides, which helps us anticipate where a dispute is likely to go.