The right to manage lets the leaseholders of a block of flats in England and Wales take over the management of their building from the landlord, without having to prove the landlord has done anything wrong and without buying the freehold. It comes from Part 2, Chapter 1 of the Commonhold and Leasehold Reform Act 2002, and since 3 March 2025 it has been easier and cheaper to use: buildings with up to 50% commercial floor space can now qualify, and the leaseholders’ company no longer has to pay the landlord’s costs of the claim in most cases.
This guide explains what the right to manage gives you, which buildings qualify, how a right to manage company is set up and run, the statutory process step by step, what it costs and what changes once the company takes over. If your building is weighing up a claim, our right to manage and enfranchisement team can tell you quickly whether you qualify and what the risks are.

What the right to manage is, and what it is not
Right to manage (often shortened to RTM) is a transfer of management, not ownership. The landlord keeps the freehold, keeps receiving ground rent and remains the landlord under every lease. What moves to the leaseholders’ company is the landlord’s management role under the leases: collecting and spending the service charge, arranging repairs and maintenance, insuring the building where the lease puts that on the landlord, appointing (or dismissing) a managing agent and dealing with day-to-day issues in the common parts.
The key feature is that it is a “no fault” right. Leaseholders do not need to show poor management, excessive charges or any breach by the landlord. If the building qualifies and the correct procedure is followed, the landlord cannot stop the claim, although it can dispute whether the company is entitled to it.
| Moves to the RTM company | Stays with the landlord |
|---|---|
| Setting, collecting and spending the service charge | Ownership of the freehold and the right to sell it |
| Repairs, maintenance and cleaning of the structure and common parts | Ground rent |
| Building insurance, where the lease makes that the landlord’s job | Forfeiture and re-entry under the leases |
| Choosing and instructing a managing agent | Management of any parts not let on the flat leases (for example a commercial unit let separately) |
| Giving approvals under the leases (with notice to the landlord) | Any lease extension or freehold purchase negotiations |
Because the freehold does not change hands, the right to manage does nothing for the length of your lease or the ground rent. Leaseholders with short leases still need a lease extension, and buildings that want ownership as well as control should look at our guide to buying the freehold through collective enfranchisement.
Does your building qualify?
The qualifying rules are in section 72 of, and Schedule 6 to, the 2002 Act. A building (or a self-contained part of a building) qualifies if:
- it contains at least two flats held by “qualifying tenants”, which in practice means leaseholders with a long lease, usually one granted for more than 21 years;
- the flats held by qualifying tenants make up at least two-thirds of all the flats in the building; and
- no more than 50% of the internal floor area (ignoring common parts) is non-residential, such as shops, offices or restaurants. Until 3 March 2025 the limit was 25%, which shut out a large number of London mixed-use blocks with ground floor commercial units. Section 49 of the Leasehold and Freehold Reform Act 2024 raised it.
There are some exclusions. The right to manage does not apply where:
- the building has a resident landlord, contains no more than four units and is not a purpose-built block (typically a converted house where the freeholder or an adult family member has lived in one of the flats as their only or principal home for the last 12 months);
- a local housing authority is the immediate landlord of any qualifying tenant in the building; or
- an RTM company already has the right to manage the building, or that right ended less than four years ago (the tribunal can disapply the four-year bar where applying it would be unreasonable).
Two points catch groups out. First, there is no minimum length of time you must have owned your flat and no requirement to live there: investors and absent owners count. Second, whether part of a site is a “self-contained part of a building” can be technical, particularly on estates with several blocks sharing a basement car park or services. Get the qualification question checked before anyone spends money on notices.
Setting up a right to manage company
The claim has to be made by a right to manage company, which is a private company limited by guarantee whose articles state that acquiring and exercising the right to manage the building is one of its objects. Its articles must follow the prescribed model articles for RTM companies, and a company can only be the RTM company for one set of premises.
Every qualifying tenant in the building is entitled to become a member, and so is the landlord once the company has acquired the right to manage. The landlord can vote on the company’s decisions. Under the current model articles, the landlord gets one vote for each flat or non-residential unit it owns (with a minimum of one), but its total votes cannot exceed one-third of the votes held by the leaseholder members. That cap was introduced in 2025 to stop freeholders who own several flats from controlling the company.
For the claim itself, the company’s members must include qualifying tenants of at least half of the flats in the building. In a two-flat building, both qualifying tenants must be members.
Directors of an RTM company take on the same legal duties as directors of any other company, including filing accounts and a confirmation statement at Companies House each year. If your group has no experience of running a company, our company secretarial team can handle the filings and governance so the volunteers can concentrate on the building.
The right to manage process, step by step
The procedure is strict. A notice served on the wrong person, with the wrong dates or missing prescribed information can invalidate the claim and force the company to start again. The table below sets out the statutory steps and time limits.
| Step | What happens | Timing |
|---|---|---|
| 1. Check qualification and interest | Confirm the building qualifies, identify the landlord and any intermediate landlords or management companies party to the leases, and gauge support. | Before anything is incorporated |
| 2. Incorporate the RTM company | Company limited by guarantee formed with the prescribed articles. | Usually a few days |
| 3. Obtain information (if needed) | The company can serve notice requiring information it reasonably needs to work out who to give notices to and what the claim should say. | Response due within 28 days |
| 4. Notice of invitation to participate | Served on every qualifying tenant who is not already a member (or has not agreed to become one), inviting them to join. | At least 14 days before the claim notice |
| 5. Claim notice | Served on the landlord, any other party to the leases and any tribunal-appointed manager, with a copy to every qualifying tenant. It sets the deadline for a counter-notice and the proposed acquisition date. | Counter-notice date at least one month after service |
| 6. Counter-notice | The landlord either admits the company’s entitlement or alleges it was not entitled on the date of the claim notice. | By the date in the claim notice |
| 7. Tribunal (if disputed) | If any counter-notice disputes the claim, the company applies to the First-tier Tribunal (Property Chamber) for a determination that it is entitled. | Within two months of the counter-notice |
| 8. Handover preparation | Landlord gives contractor notices to existing service providers and the company issues its own; information and documents passed over. | Between claim and acquisition date |
| 9. Acquisition date | Management transfers. The landlord must pass over uncommitted service charge money on that date or as soon as reasonably possible. | At least three months after the counter-notice date if undisputed; three months after a tribunal decision becomes final if disputed |
In an uncontested claim, the earliest the company can take over is roughly four months after the claim notice (one month for the counter-notice plus at least three months to the acquisition date). In practice, allow for the time needed to sign up members, incorporate and prepare the notices, so five to six months from the first meeting is a realistic minimum. A disputed claim adds the tribunal timetable on top.
Landlords who dispute a claim most often point to defects in the notices, a failure to serve every qualifying tenant, an error in identifying the premises, or a question over whether the building is self-contained or within the commercial floor space limit. Those are exactly the issues that careful preparation at steps 1 to 5 avoids.
What does the right to manage cost?
The biggest change in 2025 was to costs. Before 3 March 2025, the RTM company had to pay the landlord’s reasonable costs of dealing with the claim, including the costs of tribunal proceedings, which landlords could use to make claims expensive and uncertain. Section 50 of the Leasehold and Freehold Reform Act 2024 changed that: the RTM company is no longer liable for the landlord’s costs, except where the tribunal orders costs in limited circumstances, such as a claim that is withdrawn or stops being valid. Section 64 of the same Act also stops a landlord passing its non-litigation RTM costs on through the service charge to leaseholders who are not members of the company. Each side now generally pays its own way.
That leaves the company’s own costs, which typically include:
- legal fees for checking qualification, incorporating the company and preparing and serving the notices;
- any tribunal application fees and representation if the landlord disputes the claim;
- a managing agent’s fees, if the company appoints one, from the acquisition date onwards;
- directors’ and officers’ insurance and the ongoing cost of running the company (accounts and filings).
The total depends heavily on the size of the building, how organised the leaseholders are and whether the landlord fights the claim. Most groups divide the set-up costs between the participating members.
After the takeover: running the building
On the acquisition date the RTM company steps into the landlord’s management shoes and takes on its obligations as well as its powers. In practice that means:
- Service charges. The company becomes responsible for budgeting, demanding and accounting for the service charge in line with the leases and the Landlord and Tenant Act 1985, including holding service charge money on trust. Leaseholders keep their statutory rights against the company, so the rules in our guide to challenging service charges apply to an RTM company just as they would to a landlord.
- Major works consultation. If the company plans works that would cost any leaseholder more than £250, or enters long-term agreements over £100 a year per leaseholder, it must follow the section 20 consultation process.
- Approvals. Where the leases require the landlord’s consent (for example to assign, sublet or carry out alterations), the company now gives it, but it must notify the landlord first: at least 30 days’ notice for assignments, subletting, charging and structural alterations or changes of use, and at least 14 days for other approvals.
- Building safety and insurance. Directors need to understand fire safety duties, any obligations under the Building Safety Act 2022 for taller buildings, and the insurance covenant in the leases.
Most RTM companies appoint a managing agent to handle the day-to-day work, with the directors setting the budget and holding the agent to account. The advantage over the old position is that the leaseholders choose the agent and can replace it.
Right to manage or buy the freehold?
Right to manage is usually quicker and cheaper than collective enfranchisement because there is no purchase price to pay and fewer leaseholders are needed to take part in practice. But it gives control, not ownership. Buying the freehold also brings the ability to grant long lease extensions without paying a premium to an outside landlord, an end to ground rent and the right to deal with the building as owners. We compare the two in detail in right to manage vs buying the freehold.
What the 2026 reforms mean for RTM
The Commonhold and Leasehold Reform Bill, introduced to Parliament on 19 November 2026, proposes further changes the government describes as an easier and cheaper way for leaseholders to take control of their building. It is a Bill, not law, and the detail may change as it goes through Parliament. Separately, new service charge information rights for leaseholders start on 1 April 2027, with standardised service charge demands and annual reports for private landlords following on 1 November 2027 under regulations laid in November 2026. RTM companies that already manage a building, or groups planning a claim now, should factor those reporting duties into how they will run the building and what kind of managing agent they need.
Frequently asked questions
Do we need the landlord’s permission?
No. If the building qualifies and the procedure is followed correctly, the landlord cannot refuse. It can only dispute whether the company is entitled on the facts, and the tribunal decides.
Do all leaseholders have to join?
No. Members must include qualifying tenants of at least half of the flats. Leaseholders who do not join still benefit from the new management and still pay service charges under their leases, but they do not vote.
Can a commercial tenant or shop owner stop the claim?
Not on that basis alone. Provided the non-residential floor area is no more than 50% of the internal floor area, a mixed-use building can qualify. The commercial units are not qualifying flats, but they do count towards the floor area calculation.
Can the landlord take management back?
Not while the RTM company is entitled to manage. The right to manage only ends in limited situations, for example by agreement with the landlord, if the company is wound up, if a tribunal appoints a manager or if the building stops qualifying.
What is an RTM company?
An RTM company is the company leaseholders use to claim and exercise the right to manage. Under section 73 of the Commonhold and Leasehold Reform Act 2002 it must be a private company limited by guarantee whose articles state that acquiring and exercising the right to manage the premises is one of its objects, and it can only act for one set of premises.
What are the legal responsibilities of an RTM company?
Once it takes over, the RTM company takes on the landlord’s management obligations as well as its powers. That includes budgeting, demanding and accounting for service charges, consulting under section 20 before major works, dealing with insurance and building safety, and giving lease approvals after notifying the landlord. Its directors also have the ordinary duties of company directors, including annual filings at Companies House.
Next steps
The right to manage is one of the most effective tools leaseholders have, but it rewards preparation. The work that matters most is done before the claim notice goes out: confirming the building qualifies, identifying every party who must be served and getting the dates and content of each notice right. We act for leaseholder groups taking control of their buildings and for freeholders responding to claims, so we know where claims tend to fail.
If your building is considering a claim, or you have received a claim notice as a landlord, speak to our right to manage solicitors about your building. Call us on +44 207 566 1188 or email info@gurvelegal.com.